Construction of a water station combined with an 11 m high wind-catcher tower as a central village object and prototype. The installation is made of locally available building materials such as natural stone, metal, concrete and wooden poles. An old open water cistern, 7 m long and 4 m wide, was converted into the wind-cooled common room of 28 m² on the ground floor. To do this, the walls were opened on all four sides and the demolition material was used to build a “recycling seating installation” in front of the tower. The stone rubble was layered into seven gabions, some of whose tops were smoothed with mortar. Together with the tower’s surrounding seating steps, this created a grandstand for the adjacent football pitch.
On top of the 11.4 m high and 3 m wide tower sits a funnel in the shape of an inverted pyramid which, following the principle of traditional wind-catcher towers, channels the wind through a double-walled corrugated iron cylinder into the former cistern room. This creates a naturally air-conditioned, shaded common room that also provides water.
For the water supply, two water tanks are arranged one above the other at the centre of the tower, with a total capacity of 8,000 litres.
Fig. left: tower with wind-catcher pyramid, roof, external ventilation shaft and two water tanks arranged one above the other at the centre of the tower; ground floor with airflow through ceiling openings in the common room, water tap and water trough.

Wind-Wasser-Turm
Michamvi, Zanzibar, Tanzania, 2016
Construction of a water station combined with an 11 m high wind-catcher tower as a central village object and prototype. The installation is made of locally available building materials such as natural stone, metal, concrete and wooden poles. An old open water cistern, 7 m long and 4 m wide, was converted into the wind-cooled common room of 28 m² on the ground floor. To do this, the walls were opened on all four sides and the demolition material was used to build a “recycling seating installation” in front of the tower. The stone rubble was layered into seven gabions, some of whose tops were smoothed with mortar. Together with the tower’s surrounding seating steps, this created a grandstand for the adjacent football pitch.
On top of the 11.4 m high and 3 m wide tower sits a funnel in the shape of an inverted pyramid which, following the principle of traditional wind-catcher towers, channels the wind through a double-walled corrugated iron cylinder into the former cistern room. This creates a naturally air-conditioned, shaded common room that also provides water.
For the water supply, two water tanks are arranged one above the other at the centre of the tower, with a total capacity of 8,000 litres.
Fig. left: tower with wind-catcher pyramid, roof, external ventilation shaft and two water tanks arranged one above the other at the centre of the tower; ground floor with airflow through ceiling openings in the common room, water tap and water trough.

Wind-Wasser-Turm
Michamvi, Zanzibar, Tanzania, 2016
Construction of a water station combined with an 11 m high wind-catcher tower as a central village object and prototype. The installation is made of locally available building materials such as natural stone, metal, concrete and wooden poles. An old open water cistern, 7 m long and 4 m wide, was converted into the wind-cooled common room of 28 m² on the ground floor. To do this, the walls were opened on all four sides and the demolition material was used to build a “recycling seating installation” in front of the tower. The stone rubble was layered into seven gabions, some of whose tops were smoothed with mortar. Together with the tower’s surrounding seating steps, this created a grandstand for the adjacent football pitch.
On top of the 11.4 m high and 3 m wide tower sits a funnel in the shape of an inverted pyramid which, following the principle of traditional wind-catcher towers, channels the wind through a double-walled corrugated iron cylinder into the former cistern room. This creates a naturally air-conditioned, shaded common room that also provides water.
For the water supply, two water tanks are arranged one above the other at the centre of the tower, with a total capacity of 8,000 litres.
Fig. left: tower with wind-catcher pyramid, roof, external ventilation shaft and two water tanks arranged one above the other at the centre of the tower; ground floor with airflow through ceiling openings in the common room, water tap and water trough.

Wind-Wasser-Turm
Michamvi, Zanzibar, Tanzania, 2016
Construction of a water station combined with an 11 m high wind-catcher tower as a central village object and prototype. The installation is made of locally available building materials such as natural stone, metal, concrete and wooden poles. An old open water cistern, 7 m long and 4 m wide, was converted into the wind-cooled common room of 28 m² on the ground floor. To do this, the walls were opened on all four sides and the demolition material was used to build a “recycling seating installation” in front of the tower. The stone rubble was layered into seven gabions, some of whose tops were smoothed with mortar. Together with the tower’s surrounding seating steps, this created a grandstand for the adjacent football pitch.
On top of the 11.4 m high and 3 m wide tower sits a funnel in the shape of an inverted pyramid which, following the principle of traditional wind-catcher towers, channels the wind through a double-walled corrugated iron cylinder into the former cistern room. This creates a naturally air-conditioned, shaded common room that also provides water.
For the water supply, two water tanks are arranged one above the other at the centre of the tower, with a total capacity of 8,000 litres.
Fig. left: tower with wind-catcher pyramid, roof, external ventilation shaft and two water tanks arranged one above the other at the centre of the tower; ground floor with airflow through ceiling openings in the common room, water tap and water trough.

In the second tank, rainwater from the roof can be collected and used as non-potable service water for everyday tasks that do not require potable water. In most places on Zanzibar, the water comes from wells, which are frequently contaminated or saline.
As part of a German pilot project, drinking water that has been purified and desalinated is pumped in Michamvi through a pipeline from a well some 10 km away into one of the two tanks.
Partners
The GIZ public-private partnership project was implemented in cooperation with German companies and the Zanzibar Water Authority (ZAWA), the local water supplier.
Collaboration/Funding
Knowledge Exchange – Verein zur Förderung des internationalen Wissensaustauschs, Munich, Germany; wind-catcher technology: Chair of Building Technology and Climate Responsive Design,
Prof. Thomas Auer, Technical University of Munich (TUM), assisted by Elisabeth Endres and Daniele Santucci; project management and technical implementation on site: Christoph Helf, Zanzibar, Tanzania; consultancy/project development: Dipl.-Ing. Andreas Zeiselmair, Munich; structural design: Dipl.-Ing. Jonas Schikore, Munich. Design, concept and realisation: Markus Heinsdorff; construction by local craftsmen.
In the second tank, rainwater from the roof can be collected and used as non-potable service water for everyday tasks that do not require potable water. In most places on Zanzibar, the water comes from wells, which are frequently contaminated or saline.
As part of a German pilot project, drinking water that has been purified and desalinated is pumped in Michamvi through a pipeline from a well some 10 km away into one of the two tanks.
Partners
The GIZ public-private partnership project was implemented in cooperation with German companies and the Zanzibar Water Authority (ZAWA), the local water supplier.
Collaboration/Funding
Knowledge Exchange – Verein zur Förderung des internationalen Wissensaustauschs, Munich, Germany; wind-catcher technology: Chair of Building Technology and Climate Responsive Design,
Prof. Thomas Auer, Technical University of Munich (TUM), assisted by Elisabeth Endres and Daniele Santucci; project management and technical implementation on site: Christoph Helf, Zanzibar, Tanzania; consultancy/project development: Dipl.-Ing. Andreas Zeiselmair, Munich; structural design: Dipl.-Ing. Jonas Schikore, Munich. Design, concept and realisation: Markus Heinsdorff; construction by local craftsmen.
In the second tank, rainwater from the roof can be collected and used as non-potable service water for everyday tasks that do not require potable water. In most places on Zanzibar, the water comes from wells, which are frequently contaminated or saline.
As part of a German pilot project, drinking water that has been purified and desalinated is pumped in Michamvi through a pipeline from a well some 10 km away into one of the two tanks.
Partners
The GIZ public-private partnership project was implemented in cooperation with German companies and the Zanzibar Water Authority (ZAWA), the local water supplier.
Collaboration/Funding
Knowledge Exchange – Verein zur Förderung des internationalen Wissensaustauschs, Munich, Germany; wind-catcher technology: Chair of Building Technology and Climate Responsive Design,
Prof. Thomas Auer, Technical University of Munich (TUM), assisted by Elisabeth Endres and Daniele Santucci; project management and technical implementation on site: Christoph Helf, Zanzibar, Tanzania; consultancy/project development: Dipl.-Ing. Andreas Zeiselmair, Munich; structural design: Dipl.-Ing. Jonas Schikore, Munich. Design, concept and realisation: Markus Heinsdorff; construction by local craftsmen.


Disused former cistern before conversion

Opening the cistern walls

Recycling the demolition stones for seating gabions


Disused former cistern before conversion

Opening the cistern walls

Recycling the demolition stones for seating gabions


Disused former cistern before conversion

Opening the cistern walls

Recycling the demolition stones for seating gabions

Openings of the wind ducts in the ceiling of the common room

Water supply on foot, by bicycle or by cart


Openings of the wind ducts in the ceiling of the common room

Water supply on foot, by bicycle or by cart


Openings of the wind ducts in the ceiling of the common room

Water supply on foot, by bicycle or by cart


The gabions, seating steps and the open space of the water station serve as seating...


... during football matches on the adjacent village square

The gabions, seating steps and the open space of the water station serve as seating...


... during football matches on the adjacent village square

The gabions, seating steps and the open space of the water station serve as seating...


... during football matches on the adjacent village square
©
2026
Markus Heinsdorff Copyright.
©
2026
Markus Heinsdorff Copyright.
©
2026
Markus Heinsdorff Copyright.
©
2026
Markus Heinsdorff Copyright.